Filters
Question type

Study Flashcards

The standard factory overhead rate is $10 per direct labor hour ($8 for variable factory overhead and $2 for fixed factory overhead) based on 100% of normal capacity of 30,000 direct labor hours. The standard cost and the actual cost of factory overhead for the production of 5,000 units during May were as follows: The standard factory overhead rate is $10 per direct labor hour ($8 for variable factory overhead and $2 for fixed factory overhead)  based on 100% of normal capacity of 30,000 direct labor hours. The standard cost and the actual cost of factory overhead for the production of 5,000 units during May were as follows:   ​ -The fixed factory overhead volume variance is A) $12,500 favorable B) $10,000 unfavorable C) $12,500 unfavorable D) $10,000 favorable ​ -The fixed factory overhead volume variance is


A) $12,500 favorable
B) $10,000 unfavorable
C) $12,500 unfavorable
D) $10,000 favorable

E) A) and B)
F) A) and D)

Correct Answer

verifed

verified

The standard factory overhead rate is $7.50 per machine hour ($6.20 for variable factory overhead and $1.30 for fixed factory overhead) based on 100% of normal capacity of 80,000 machine hours. The standard cost and the actual cost of factory overhead for the production of 15,000 units during August were as follows: The standard factory overhead rate is $7.50 per machine hour ($6.20 for variable factory overhead and $1.30 for fixed factory overhead)  based on 100% of normal capacity of 80,000 machine hours. The standard cost and the actual cost of factory overhead for the production of 15,000 units during August were as follows:   ​ -The unfavorable volume variance may be due to all of the following factors except A) failure to maintain an even flow of work B) machine breakdowns C) unexpected increases in the cost of utilities D) failure to obtain enough sales orders ​ -The unfavorable volume variance may be due to all of the following factors except


A) failure to maintain an even flow of work
B) machine breakdowns
C) unexpected increases in the cost of utilities
D) failure to obtain enough sales orders

E) A) and B)
F) C) and D)

Correct Answer

verifed

verified

The standard factory overhead rate is $7.50 per machine hour ($6.20 for variable factory overhead and $1.30 for fixed factory overhead) based on 100% of normal capacity of 80,000 machine hours. The standard cost and the actual cost of factory overhead for the production of 15,000 units during August were as follows: The standard factory overhead rate is $7.50 per machine hour ($6.20 for variable factory overhead and $1.30 for fixed factory overhead)  based on 100% of normal capacity of 80,000 machine hours. The standard cost and the actual cost of factory overhead for the production of 15,000 units during August were as follows:   ​ -The controllable variance measures A) operating results at less than normal capacity B) the efficiency of using variable overhead resources C) operating results at more than normal capacity D) control over fixed overhead costs ​ -The controllable variance measures


A) operating results at less than normal capacity
B) the efficiency of using variable overhead resources
C) operating results at more than normal capacity
D) control over fixed overhead costs

E) A) and B)
F) A) and C)

Correct Answer

verifed

verified

Accounting systems that use standards for product costs are called variable cost systems.

A) True
B) False

Correct Answer

verifed

verified

Standard and actual costs for direct labor for the manufacture of 1,000 units of product were as follows: Standard and actual costs for direct labor for the manufacture of 1,000 units of product were as follows:   Determine the direct labor (a) time variance, (b) rate variance, and (c) total cost variance. Determine the direct labor (a) time variance, (b) rate variance, and (c) total cost variance.

Correct Answer

verifed

verified

The direct labor time variance is the difference between the


A) actual labor rate and the standard labor rate
B) actual costs and standard costs
C) actual hours at the standard rate and the standard costs
D) actual costs and the actual hours at the standard rate

E) A) and B)
F) C) and D)

Correct Answer

verifed

verified

Titus Company produced 8,900 units of a product that required 3.25 standard hours per unit. The standard fixed overhead cost per unit is $1.20 per hour at 29,000 hours, which is 100% of normal capacity.​ Determine the fixed factory overhead volume variance.

Correct Answer

verifed

verified

The fixed factory overhead vol...

View Answer

Compute the direct labor rate and time variances for Taylor Company.

Correct Answer

verifed

verified

Direct labor rate variance: $6...

View Answer

If the standard to produce a given amount of product is 1,000 units of direct materials at $11 and the actual direct materials used are 800 units at $12, the direct materials price variance is $800 favorable.

A) True
B) False

Correct Answer

verifed

verified

The standard factory overhead rate is $7.50 per machine hour ($6.20 for variable factory overhead and $1.30 for fixed factory overhead) based on 100% of normal capacity of 80,000 machine hours. The standard cost and the actual cost of factory overhead for the production of 15,000 units during August were as follows: The standard factory overhead rate is $7.50 per machine hour ($6.20 for variable factory overhead and $1.30 for fixed factory overhead)  based on 100% of normal capacity of 80,000 machine hours. The standard cost and the actual cost of factory overhead for the production of 15,000 units during August were as follows:   ​ -The variable factory overhead controllable variance is A) $12,000 unfavorable B) $12,000 favorable C) $14,000 unfavorable D) $26,000 unfavorable ​ -The variable factory overhead controllable variance is


A) $12,000 unfavorable
B) $12,000 favorable
C) $14,000 unfavorable
D) $26,000 unfavorable

E) All of the above
F) A) and B)

Correct Answer

verifed

verified

The standard costs and actual costs for factory overhead for the manufacture of 2,500 units of actual production are as follows: Standard Costs Fixed overhead (based on 10,000 hours) 3 hours per unit at $0.80 per hour Variable overhead 3 hours per unit at $2.00 per hour Actual Costs Total variable cost, $18,000 Total fixed cost, $8,000 -The fixed factory overhead volume variance is


A) $2,000 favorable
B) $2,000 unfavorable
C) $2,500 unfavorable
D) $0

E) C) and D)
F) B) and D)

Correct Answer

verifed

verified

The following data relate to direct labor costs for February: Actual costs 7,700 hours at $14.00 Standard costs 7,000 hours at $16.00 -The direct labor rate variance is


A) $14,000 favorable
B) $14,000 unfavorable
C) $15,400 favorable
D) $15,400 unfavorable

E) A) and C)
F) A) and B)

Correct Answer

verifed

verified

The variance from standard for factory overhead cost resulting from operating at a level above or below 100% of normal capacity is termed volume variance.

A) True
B) False

Correct Answer

verifed

verified

Tucker Company produced 8,900 units of product that required 3.25 standard hours per unit. The standard variable overhead cost per unit is $4.00 per hour. The actual variable factory overhead was $111,000.​ Determine the variable factory overhead controllable variance.

Correct Answer

verifed

verified

The variable factory overhead ...

View Answer

Although favorable fixed factory overhead volume variances are usually good news, if inventory levels are too high, additional production could be harmful.

A) True
B) False

Correct Answer

verifed

verified

The following data relate to direct labor costs for August: actual costs for 5,500 hours at $24.00 per hour and standard costs for 5,000 hours at $23.70 per hour.​ The direct labor rate variance is


A) $1,650 favorable
B) $1,650 unfavorable
C) $1,500 favorable
D) $1,500 unfavorable

E) C) and D)
F) All of the above

Correct Answer

verifed

verified

The standard factory overhead rate is $10 per direct labor hour ($8 for variable factory overhead and $2 for fixed factory overhead) based on 100% of normal capacity of 30,000 direct labor hours. The standard cost and the actual cost of factory overhead for the production of 5,000 units during May were as follows: The standard factory overhead rate is $10 per direct labor hour ($8 for variable factory overhead and $2 for fixed factory overhead)  based on 100% of normal capacity of 30,000 direct labor hours. The standard cost and the actual cost of factory overhead for the production of 5,000 units during May were as follows:   ​ -Assuming that the standard fixed overhead rate is based on full capacity, the cost of available but unused productive capacity is indicated by the A) fixed factory overhead volume variance B) direct labor time variance C) direct labor rate variance D) variable factory overhead controllable variance ​ -Assuming that the standard fixed overhead rate is based on full capacity, the cost of available but unused productive capacity is indicated by the


A) fixed factory overhead volume variance
B) direct labor time variance
C) direct labor rate variance
D) variable factory overhead controllable variance

E) C) and D)
F) A) and B)

Correct Answer

verifed

verified

The direct labor time variance measures the efficiency of the direct labor force.

A) True
B) False

Correct Answer

verifed

verified

The direct materials quantity variance is the difference between the


A) actual costs and standard costs
B) standard quantity and the actual quantity
C) actual quantity at the standard price and the standard costs
D) actual costs and the standard price at the standard quantity

E) All of the above
F) C) and D)

Correct Answer

verifed

verified

Match each of the following phrases with the term (a-e) it describes. -Theoretical standard


A) Ideal standard
B) Normal standard
C) Budget performance report
D) Unfavorable cost variance
E) Favorable cost variance

F) All of the above
G) A) and B)

Correct Answer

verifed

verified

Showing 21 - 40 of 172

Related Exams

Show Answer