Filters
Question type

Study Flashcards

Mansi Inc. is considering a project that has the following cash flow data. What is the project's payback?


A) 1.91 years
B) 2.12 years
C) 2.36 years
D) 2.59 years
E) 2.85 years

F) B) and E)
G) All of the above

Correct Answer

verifed

verified

In theory, capital budgeting decisions should depend solely on forecasted cash flows and the opportunity cost of capital. The decision criterion should not be affected by managers' tastes, choice of accounting method, or the profitability of other independent projects.

A) True
B) False

Correct Answer

verifed

verified

Nast Inc. is considering Projects S and L, whose cash flows are shown below. These projects are mutually exclusive, equally risky, and not repeatable. If the decision is made by choosing the project with the higher MIRR rather than the one with the higher NPV, how much value will be forgone? Note that under some conditions choosing projects on the basis of the MIRR will cause $0.00 value to be lost.


A) $32.12
B) $35.33
C) $38.87
D) $40.15
E) $42.16

F) B) and C)
G) None of the above

Correct Answer

verifed

verified

Which of the following statements is CORRECT?


A) For a project with normal cash flows, any change in the WACC will change both the NPV and the IRR.
B) To find the MIRR, we first compound cash flows at the regular IRR to find the TV, and then we discount the TV at the WACC to find the PV.
C) The NPV and IRR methods both assume that cash flows can be reinvested at the WACC. However, the MIRR method assumes reinvestment at the MIRR itself.
D) If two projects have the same cost, and if their NPV profiles cross in the upper right quadrant, then the project with the higher IRR probably has more of its cash flows coming in the later years.
E) If two projects have the same cost, and if their NPV profiles cross in the upper right quadrant, then the project with the lower IRR probably has more of its cash flows coming in the later years.

F) A) and E)
G) B) and C)

Correct Answer

verifed

verified

Which of the following statements is CORRECT?


A) For a project to have more than one IRR, then both IRRs must be greater than the WACC.
B) If two projects are mutually exclusive, then they are likely to have multiple IRRs.
C) If a project is independent, then it cannot have multiple IRRs.
D) Multiple IRRs can occur only if the signs of the cash flows change more than once.
E) If a project has two IRRs, then the smaller one is the one that is most relevant, and it should be accepted and relied upon.

F) B) and C)
G) A) and E)

Correct Answer

verifed

verified

Projects S and L are equally risky, mutually exclusive, and have normal cash flows. Project S has an IRR of 15%, while Project L's IRR is 12%. The two projects have the same NPV when the WACC is 7%. Which of the following statements is CORRECT?


A) If the WACC is 10%, both projects will have positive NPVs.
B) If the WACC is 6%, Project S will have the higher NPV.
C) If the WACC is 13%, Project S will have the lower NPV.
D) If the WACC is 10%, both projects will have a negative NPV.
E) Project S's NPV is more sensitive to changes in WACC than Project L's.

F) B) and E)
G) C) and D)

Correct Answer

verifed

verified

Kosovski Company is considering Projects S and L, whose cash flows are shown below. These projects are mutually exclusive, equally risky, and are not repeatable. If the decision is made by choosing the project with the higher IRR, how much value will be forgone? Note that under some conditions choosing projects on the basis of the IRR will cause $0.00 value to be lost.


A) $11.45
B) $12.72
C) $14.63
D) $16.82
E) $19.35

F) B) and E)
G) A) and D)

Correct Answer

verifed

verified

Showing 101 - 107 of 107

Related Exams

Show Answer