A) 1.91 years
B) 2.12 years
C) 2.36 years
D) 2.59 years
E) 2.85 years
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) $32.12
B) $35.33
C) $38.87
D) $40.15
E) $42.16
Correct Answer
verified
Multiple Choice
A) For a project with normal cash flows, any change in the WACC will change both the NPV and the IRR.
B) To find the MIRR, we first compound cash flows at the regular IRR to find the TV, and then we discount the TV at the WACC to find the PV.
C) The NPV and IRR methods both assume that cash flows can be reinvested at the WACC. However, the MIRR method assumes reinvestment at the MIRR itself.
D) If two projects have the same cost, and if their NPV profiles cross in the upper right quadrant, then the project with the higher IRR probably has more of its cash flows coming in the later years.
E) If two projects have the same cost, and if their NPV profiles cross in the upper right quadrant, then the project with the lower IRR probably has more of its cash flows coming in the later years.
Correct Answer
verified
Multiple Choice
A) For a project to have more than one IRR, then both IRRs must be greater than the WACC.
B) If two projects are mutually exclusive, then they are likely to have multiple IRRs.
C) If a project is independent, then it cannot have multiple IRRs.
D) Multiple IRRs can occur only if the signs of the cash flows change more than once.
E) If a project has two IRRs, then the smaller one is the one that is most relevant, and it should be accepted and relied upon.
Correct Answer
verified
Multiple Choice
A) If the WACC is 10%, both projects will have positive NPVs.
B) If the WACC is 6%, Project S will have the higher NPV.
C) If the WACC is 13%, Project S will have the lower NPV.
D) If the WACC is 10%, both projects will have a negative NPV.
E) Project S's NPV is more sensitive to changes in WACC than Project L's.
Correct Answer
verified
Multiple Choice
A) $11.45
B) $12.72
C) $14.63
D) $16.82
E) $19.35
Correct Answer
verified
Showing 101 - 107 of 107
Related Exams